When creating move timelines, we need to consider a number of factors as each project is unique. This includes the type and size of the house being shifted, having approved consents for the new site, infrastructure set up and more.

Once you own land and have found the right house, allow for the following time:

  • 6-8 weeks is feasible for floor plans, site plans, foundation plans, Geotech reports and drainage plans. It is important to remember that every day is crucial at this stage of the process.
  • 2 weeks to prepare for your Building Consent (gathering everything on the Building Consent Checklist from your Council). We have a team that will help you with this
  • 20 working days for the building consent process once you’ve submitted your forms to your Council.

Once building consent is granted, you can start connection of services and other trades that you might need to get your house ready for sign-off with council.

Our team can assist with all the steps and consents needed within this process, and are here to assist you right throughout the journey.